Aim: Design workshop to run with users and plan next two weeks
Approx. 2 weeks to submission
Plan
22-25 May: Lilly to write up workshop design, all group members to run workshop with at least one potential installation participant (can be a UQ student, but not from our class). Each member to write a blog post about the workshop and concept feedback from workshop.WORKSHOP BLOG POST due Monday 25 May (before group meeting at 1pm)
26-31 May: Complete Design Intent Document, Sucess Criteria, Frame Analysis
Monday 1 June, 1pm: RUN INSTALLATION
1-4 June: Complete User Evaluation and process video footage
5 June: Project 2: Phase 2 DUE
Other upcoming items:
Thursday 21 May: Upload workshop design document to Google Plus (done)Friday 22 May: Film & upload bodystorm of concept to Google Plus for Team Critique (done)
Wednesday 27 May: Post 2 team critiques for other group's bodystorms on Google Plus & submit to BlackBoard
Friday 29 May: Next Journal Entry due